FACTOID
Daily track capacity by the numbers
TWC-TRACK WARRANT CONTROL
ABS-AUTOMATIC BLOCK SIGNALS
CTC-CENTRALIZED TRAFFIC CONTROL
DARK-NO SIGNAL SYSTEM
CAPACITY EXPRESSED IN NUMBER OF TRAINS PER 24 HOUR PERIOD
SINGLE TRACK (TWC)/DARK 16-20
SINGLE TRACK (TWC)/ABS 18-25
DOUBLE TRACK (TWC)/DARK 28-35
DOUBLE TRACK (TWC)/ABD 53-80
SINGLE TRACK (CTC) 30-48
TWO MAIN TRACK (CTC) 75-100
THREE MAIN TRACK (CTC) 133-163
Congestion begins at about 70% of capacity (first number).
Source: BNSF Railway